West Camden Water Treatment Plant

 

2021/2024

UPGRADE OF TREATMENT PLANT

Downer-BMD JV – $14.9 million

  • Bulk Excavation of 90,000 m3
  • Removal of General Solid Waste
  • Supply and filling of 75,000 Tons of DGS40 for Sub Grade
  • Asbestos Management and Disposal of 10,800 m3
  • Permeate Outfall 1000mm Pipe with Flow Meter and Tie into Concrete Structures
  • Form Reo Pour Flowmeter Pit 4 X 5m X 4.5m Deep
  • Equalization Basin 1000mm Pipework and Tie In
  • Chemical Dosing Lines and Testing
  • Recycled Effluent Pipe and Testing
  • Electrical Conduits and Precast Pits